A Few More Things
Dave poured a pad for our smaller HVAC unit. Both the patios and the HVAC work are scheduled to begin this week. Actually Monday, but we've seen the concrete work slide a few days before. Most of the lighting is in with the rest due in Monday. A few electrical items have to wait for the tilers to do their thing. Now we have to do some rip rapping on our slopes and neaten the 'yard' up. We still need a bobcat to come do some leveling of the areas right next to the house and then we have to grade for the driveway.
The count of lots either done, under construction, or in the permitting process is now up to 8!